Thane-Mulund Railway Station faces hurdles in land transfer – Details Inside
时间:2024-06-25 14:04:50 阅读(143)
The progress on the proposed railway station between Thane and Mulund is facing significant delays as the Maharashtra government’s health department has not yet handed over a crucial four-acre land parcel to the Indian Railways, Shiv Sena (UBT) MP from Thane, Rajan Vichare, claimed on Saturday. The unresolved land transfer issue becomes a major roadblock in the timely completion of the railway station project.Obstacles Beyond Land Transfer
Beyond the land transfer predicament, MP Rajan Vichare highlighted the additional challenge of slum encroachment on the earmarked land, further contributing to the delays in the proposed railway station’s construction. The presence of slums exacerbates the complexity of the project, requiring coordinated efforts to address the issue.
On-Site Inspection HighlightsMP Rajan Vichare conducted an inspection of facilities at Thane railway station, providing insights into the ongoing projects. According to an official release, the work completion status for three approach roads, the station deck, parking facilities, and the compound wall for the proposed Thane-Mulund railway station stands at 30 percent. The inspection sheds light on the progress achieved amidst the challenges.
Legal Clearance for Land TransferEarlier this year, the Bombay High Court removed a stay on the transfer of part of Thane Mental Hospital’s land for the railway station construction. The court’s decision allowed the transfer of more than 14 acres of the hospital’s land, out of its total 72 acres, for the new railway station. This legal clearance overcame a significant hurdle, paving the way for the project’s progression.
Warm Welcome for Jalna-CSMT Vande Bharat Express: A Bright SpotDespite the hurdles, Shiv Sena (UBT) activists and other supporters welcomed the Jalna-CSMT Vande Bharat Express at Thane station. The train, flagged off via video link by Prime Minister Modi from Ayodhya, brought a positive moment to the railway community, offering a glimpse of celebration amidst the ongoing challenges.
(With PTI Inputs)
上一篇:OYO to refile updated draft IPO papers with SEBI by mid-February
下一篇:ZED scheme- Financial support extended to MSMEs crosses Rs 100 crore
猜你喜欢
- ITC, Mahindra & Mahindra at fresh 52-week highs on BSE; Future Consumer, Andhra Cements at new 52-week lows
- ITC only Sensex stock in green as share price jumps 4% after Q4 profit beats estimates; should you buy now-
- PayMate plans IPO in 6-9 months
- ITC, HCL Tech, Adani Ports, Equitas Small Finance Bank, IndusInd Bank, NBCC stocks in focus
- Cipla soars on buzz of Blackstone stake buy
- Cipla stock jumps 9% today on strong Q1 results; should you buy, sell or hold Cipla shares- Check target price
- Paytm Recap 2023- 912 crore merchant payments made via Paytm in Q2FY24; Delhi made most payments between 12-6 am
- Petrol and diesel price July 7- Fuel rates unchanged; Check prices in Delhi, Mumbai, other cities here
- OPEC+ cuts ahead of winter fan global inflation concerns